Construction Activities
Work will occur during daytime hours unless otherwise noted.
SR-134 to Magnolia Boulevard
Providencia Bridge: Crews are working on the deck for the bridge.
Empire Avenue: Crews are constructing concrete barrier.
Buena Vista/Winona Undercrossing: Crews are building concrete walls between abutments (the end of the bridge).
Northbound San Fernando Boulevard between Empire Avenue and Northbound I-5 on-ramp: Crews are installing a temporary barrier for clearing slopes.
Victory Place Separation: Crews are backfilling abutment walls, erecting falsework, and removing shoring.
Northbound I-5 between Buena Vista Street and Cohasset Street: Crews are constructing retaining walls and removing trees and other vegetation along San Fernando Boulevard.
Southbound I-5 at Buena Vista Street: Crews are constructing approach slabs and constructing concrete barrier.
Southbound I-5 between Buena Vista Street and Burbank Boulevard:

SR-134 to Magnolia Boulevard
Intermittent nighttime lane closures on both northbound and southbound I-5 — weekdays from 10 p.m. to 6 a.m. and weekends from 10 p.m. to 8 a.m.
Intermittent Daytime Closures on Flower Street.
Buena Vista Street Closures.
Intermittent daytime and nighttime closures of Buena Vista Street, in both directions, between San Fernando Boulevard and Winona Avenue.
The post Caltrans Gives Latest I-5 Construction Updates appeared first on myBurbank.com.